针对混合式抽水蓄能与调水耦合系统日前调度中发电、供水与调水协调困难的问题,构建多目标协同优化调度模型,采用多目标麻雀搜索算法生成非劣解集.以湖南镇-黄坛口-乌溪江混蓄系统为例,将优化模型结果与负荷分配模拟算法的基准方案进行对比,结果表明:不同目标之间存在权衡关系,发电与供水、调水呈竞争关系,供水与调水呈相容关系;相对模拟算法的基准方案,多目标优化模型的非劣解集在发电、供水和调水 3 个目标上实现提升,以枯季典型日为例,发电量提升 5.52 万 kW·h,供水保证程度提高 7.50%,外调水量增加 1.17 万 m3.本研究建立的混蓄-调水耦合多目标优化调度模型可为水网、电网系统联合调度与协同运行提供一定参考.

A multi-objective coordinated optimal scheduling model is developed for the day-ahead operation of a hybrid pumped storage-water transfer coupled system that is faced with scheduling difficulty involving how to coordinate power generation,water supply,and water transfer.It uses a multi-objective sparrow search algorithm to generate a Pareto-optimal solution set.We compare its optimization results with those of a rule-based load allocation benchmark in a case study of the Hunanzhen-Huangtankou-Wuxijiang hybrid pumped storage system.The results indicate that scheduling such a coupled system must consider significant trade-offs among the objectives-a competitive relationship of power generation versus water supply and water transfer,and an overall compatibility of water supply and water transfer.The Pareto solutions generated using this new model achieve simultaneous improvement on all the three objectives-power generation,water supply reliability,and transferred water volume-in comparison with the benchmark scheme.For a typical dry-season day,power generation increases by 55.2 MW·h,water supply reliability improves by 7.50%,and transferred water volume increases by 11,700 m3.Our scheduling model proves effective and useful for the coordinated operation of water and power networks.

姚瑶;徐斌;任梓晨;王心榕;周思盈;朱聆玮;覃馨漫

河海大学 水文水资源学院,南京 210098河海大学 水文水资源学院,南京 210098||水安全与水科学协同创新中心,南京 210098河海大学 水文水资源学院,南京 210098河海大学 水文水资源学院,南京 210098河海大学 水文水资源学院,南京 210098河海大学 水文水资源学院,南京 210098河海大学 水文水资源学院,南京 210098

建筑与水利

水库调度梯级水库群混合式抽水蓄能电站多目标优化跨区域调水日前调度

reservoir operationcascade reservoirshybrid pumped storage power stationmulti-objective optimizationinter-basin water transferday-ahead scheduling

《水力发电学报》 2026 (10)

90-99,10

国家自然科学基金项目(5227901052322902)

10.11660/slfdxb.20261009