旺港隧洞工程采用顶进施工法施工的JCCP管,在出口段隧洞贯通并进行泥浆置换回填灌浆后,位于该段中后部的管节A内侧局部出现破损.本文根据破损原因拟定多个修复方案,并从工艺难度、工期、费用和可靠性等多角度进行比选,制定不同比选项的权重,通过"加权评分法"优选出最合理的修复方案,为工程早日发挥效益提供支撑.

The Wanggang Tunnel Project adopts JCCP installed by jacking construction method.After the outlet tunnel section had been holed through and the mud displacement backfill grouting was completed,localized damage was found on the inner side of pipe segment A,which is situated in the middle-to-rear part of the said tunnel section.Based on the causes for the damage,several repair schemes were formulated and compared from multiple perspectives of construction difficulty,construction duration,cost,and reliability,with different weights assigned to each evaluation criterion.The weighted scoring method was subsequently applied to select the most reasonable repair scheme,providing support for the project to achieve its intended benefits at the earliest possible date.

周凯;龙起华

广西水利电力勘测设计研究院有限责任公司,南宁 530023广西水利电力勘测设计研究院有限责任公司,南宁 530023

建筑与水利

顶进施工法JCCP管道破损修复加权评分法旺港隧洞

jacking construction methodJacked Concrete Cylinder Pipe(JCCP)repair damaged pipeweighted scoring methodWanggang Tunnel

《广西水利水电》 2026 (5)

86-89,4