Curvature-forming mechanism and control mechanical model for directional control of curved rectangular pipe jacking
曲线矩形顶管造曲机理与方向控制是制约该技术发展的关键理论难题.本文提出了一种基于铰接式多联矩形掘进机结构与刀盘超挖协同造曲方法,建立了曲线顶进中掘进机前后盾体与地层的相互作用力学模型,实现了偏转角、地层反力与方向控制千斤顶顶力的动态精准计算.通过案例试算,系统分析了曲线半径、覆土深度、土体内摩擦角、地层抗力系数及力臂长度等关键参数对顶力分配的影响机制,验证了模型的合理性与适用性.结果表明:增大土体内摩擦角或减少覆土深度可显著降低顶力峰值;增加地层抗力系数或减小曲线半径则显著增大外侧顶力;当曲线半径小至一定阈值时,内侧顶力由正转负,掘进机由"双侧顶推"转为"外侧顶推-内侧牵拉"模式.本研究为曲线矩形顶管施工的精准控制与装备优化提供了理论依据.
The curvature-forming mechanism and directional control present key theoretical challenges restricting the advancement of curved rectangular pipe jacking technology.This study proposes an active curvature-forming method that integrates an articulated multi-unit rectangular tunneling machine with coordinated cutterhead over-excavation.A mechanical model describing the interaction between the machine's front and rear shields and the surrounding stratum during curved advancement is established,enabling dynamic and precise calculation of the deflection angle,stratum reaction force,and the required thrust of the directional control jacks.Through trial calculations of an engineering numerical case,the influence mechanisms of key parameters,including curve radius,overburden depth,soil internal friction angle,stratum reaction coefficient,and lever arm length on thrust distribution are systematically investigated,confirming the model's validity and applicability.The results demonstrate that increasing the soil internal friction angle or reducing overburden depth significantly decreases the peak thrust,whereas increasing the stratum reaction coefficient or decreasing the curve radius substantially elevates the thrust acting on the outer jack.When the curve radius decreases below a certain threshold,the inner jack thrust changes from positive to negative,causing the machine to shift from a"bilateral thrusting"mode to an"outer-side thrusting with inner-side pulling"operational pattern.This research provides a theoretical foundation for precise construction control and equipment optimization in curved rectangular pipe jacking applications.
马鹏;郑方;田小旭;宋战平;甄亮;王双院;SHIMADA Hideki
西安建筑科技大学土木工程学院,陕西 西安 710005||陕西省岩土与地下空间工程重点实验室,陕西 西安 710005西安建筑科技大学土木工程学院,陕西 西安 710005||陕西省岩土与地下空间工程重点实验室,陕西 西安 710005西安建筑科技大学土木工程学院,陕西 西安 710005||陕西省岩土与地下空间工程重点实验室,陕西 西安 710005西安建筑科技大学土木工程学院,陕西 西安 710005||陕西省岩土与地下空间工程重点实验室,陕西 西安 710005上海公路桥梁(集团)有限公司,上海 200433西安建筑科技大学土木工程学院,陕西 西安 710005九州大学地球資源工程学院,日本 福冈 8190395
交通工程
曲线矩形顶管管土相互作用成曲机制顶推力
curved rectangular pipe jackingpipe soil interactioncurvature-forming mechanismjacking force