浅水湖泊生态清淤设计底高程的分区回淤余量确定方法OA
Method for determining zonal re-siltation allowance for design bottom elevation in shallow-lake ecological dredging
针对浅水湖泊生态清淤施工图阶段设计底高程与维护期有效水深脱节的问题,提出基准底高程、分区回淤余量、约束回调确定方法.以太湖流域某13.75 km2清淤单元为例,结合双频测深、柱状底泥、硬底界面和12个月复测数据,将近岸带、入湖口影响区、开敞湖区及风浪再悬浮敏感区的余量分别确定为0.06、0.10、0.04和0.08 m.分区修正使清淤量由336.7万m3增至406.1万m3,较全湖统一预留0.12 m减少95.6万m3;复测中46个点保持在基准底高程以内,保持率95.8%.该方法可兼顾污染层清除、硬底保护、施工验收和弃淤处置,为浅水湖泊生态清淤底高程精细化设计提供依据.
To address the disconnection between the design bottom elevation at the construction drawing stage and the effective water depth during the maintenance period in ecological dredging of shallow lakes,a method for determining baseline bottom elevation,zonal re-siltation allowance and constraint-based adjustment was developed.Taking a 13.75 km2 dredging unit in the Taihu Lake Basin as an example,and combining dual-frequency sounding,sediment cores,hard bottom interface,and 12-month resurvey data,the allowances for nearshore,inlet-affected,open-water and wind-wave resuspension-sensitive zones were determined as 0.06,0.10,0.04 and 0.08 m,respectively.Zonal correction increased dredging volume from 3.367 to 4.061 million m3,which is 0.956 million m3 less than the 5.017 million m3 required under a uniform 0.12 m allowance across the entire lake.In the resurvey,46 points remained within the baseline bottom elevation,with a retention rate of 95.8%.The method balances pollutant-layer removal,hard-bottom protection,construction acceptance and disposal of dredged sediment,and provides a basis for the refined design of bottom elevation in ecological dredging of shallow lakes.
姜子岳;陈童尧;董雨航;吴永昊;王琪
江苏省太湖水利规划设计研究院有限公司,江苏 苏州 215106江苏省太湖水利规划设计研究院有限公司,江苏 苏州 215106江苏省太湖水利规划设计研究院有限公司,江苏 苏州 215106江苏省太湖水利规划设计研究院有限公司,江苏 苏州 215106江苏省太湖水利规划设计研究院有限公司,江苏 苏州 215106
资源环境
浅水湖泊生态清淤设计底高程回淤余量分区修正
shallow lakeecological dredgingdesign bottom elevationre-siltation allowancezonal correction
《江苏水利》 2026 (10)
1-4,17,5
评论