Case Study on Technical Review of Bridge Flood Control Impact Assessment
涉水建设项目技术审查过程中,应选取对河道有利的最优方案.文章以拟建的大丁圩桥梁为例,从方案建设必要性、桥梁跨度、桥墩桥桩布置、减轻影响措施等多方面进行技术审查,结合 MIKE21 二维模型对河道水位、流速流场变化等计算模拟成果,并将数值计算结果与经验公式比较,综合选择最优方案.
During the technical review process of water related construction projects,the optimal solution that is beneficial to the river channel should be selected.This article takes the proposed Dadingwei Bridge as an example to conduct technical review from multiple aspects such as the necessity of the construction plan,bridge span,arrangement of bridge piers and piles,and mitigation measures.Combined with the MIKE21 two-dimensional model,the calculation and simulation results of changes in river water level,flow velocity and field are compared with empirical formulas to comprehensively select the optimal plan.
吴志敏;于静
东莞市水务技术中心,广东 东莞 523000东莞市运河治理中心,广东 东莞 523000
交通工程
技术审查二维模型桥梁工程防洪评价
technical review2D modelbridge engineeringflood control evaluation