超浅埋复合地层插刀式矩形顶管施工及扰动控制技术研究OA
Research on Construction and Disturbance Control Technologies for Inserting-Knife Rectangular Pipe Jacking in Ultra-Shallow-Buried Composite Strata
[目的]矩形顶管在我国城市地下基础设施建设中运用广泛,且朝着超浅埋、大断面、复杂地层、长距离等方向发展.[方法]依托莆田站东侧超浅埋复合地层矩形顶管下穿运营铁路工程,详细介绍新式矩形顶管机(插刀式矩形顶管)的施工方法和近接施工安全控制技术.根据现场监测结果分析超浅埋矩形顶管近接施工扰动控制技术加固效果,并进一步分析其在复杂地质、结构环境下的施工扰动特点及致灾机理.[结果]插刀式顶管机在下穿过程中地表沉降值最大为 163.67 mm,远超过允许值,但 D 形便梁的变形均控制在安全范围内,对轨道起到关键加固作用,确保高速铁路列车的正常运营.[结论]在"D 形便梁+股道"限速为主的综合防护下,根据不同地质情况采用适应开挖方式,首次实现大断面矩形顶管机在含硬岩复杂敏感环境中安全掘进,为浅埋复杂地质条件下矩形顶管施工提供参考;结合现场监测和实际施工情况,总结插刀式矩形顶管施工过程中三类致灾机理和对应控制措施.
[Objective]Rectangular pipe jacking is widely used in urban underground infrastructure construction in China and is developing toward ultra-shallow burial,large cross sections,complex strata,and long distances.[Methods]Based on the ultra-shallow-buried rectangular pipe-jacking project in composite strata on the east side of Putian Station,which underpasses an operating railway,the construction method for a new type of rectangular pipe-jacking machine(the inserting-knife rectangular pipe-jacking machine)and the safety control technology for adjacent construction were introduced in detail.The reinforcement effect of disturbance control technology for adjacent construction of ultra-shallow-buried rectangular pipe jacking was analyzed based on the field monitoring results,and the construction disturbance characteristics and disaster-causing mechanisms in the complex geological and structural environment were further analyzed.[Results]During the underpass,the maximum surface settlement caused by the inserting-knife rectangular pipe-jacking machine was 163.67 mm,far exceeding the allowable value.However,the deformation of the D-type temporary beams remained within the safe range,and the beams played a key role in reinforcing the tracks,thereby ensuring the normal operation of high-speed railway trains.[Conclusion]Under comprehensive protection based mainly on D-type temporary beams and track speed restriction,excavation methods adapted to different geological conditions are adopted,enabling safe tunneling by a large-section rectangular pipe-jacking machine in a complex and sensitive environment containing hard rock for the first time and providing a reference for rectangular pipe-jacking construction under shallow-buried,complex geological conditions.Based on field monitoring and actual construction conditions,three types of disaster-causing mechanisms and corresponding control measures for inserting-knife rectangular pipe-jacking construction are summarized.
杨友杰;张志强;唐礼
西南交通大学土木工程学院,成都 610031西南交通大学土木工程学院,成都 610031西南交通大学土木工程学院,成都 610031
交通工程
超浅埋隧道插刀式矩形顶管复合地层D形便梁施工扰动现场监测
ultra-shallow-buried tunnelinserting-knife rectangular pipe jackingcomposite strataD-type temporary beamconstruction disturbanceon-site monitoring
《铁道标准设计》 2026 (10)
148-158,11
国家自然科学基金项目(52378414)