首页|期刊导航|华南理工大学学报(自然科学版)|富水隧道复合地层断面围岩-支护优化的数值分析

富水隧道复合地层断面围岩-支护优化的数值分析OA

Numerical Analysis of Surrounding Rock-Support Optimization for Composite Stratum Section of Water-Rich Tunnel

中文摘要英文摘要

针对杨林隧道富水围岩蠕变引发的二衬开裂问题,本研究采用已建立的水-力耦合岩石蠕变模型,并将其嵌入数值软件中进行二次开发,以实现对富水环境下围岩蠕变行为的准确模拟.在此基础上,通过收敛-约束法与正交试验相结合的手段,系统分析了不同支护参数对围岩稳定性的影响,从而确定了开裂段的新支护方案,并在实际施作过程中同步开展了现场监测,获取了关键的位移与应力数据.最后,利用该程序化模型对新支护方案下的隧道段进行了水-力耦合数值模拟,以评估其长期稳定性.结果表明:二衬开裂并非由单一因素导致,而是复合地层中断面倾斜的页岩夹层所产生的偏压效应与碳质泥岩自身蠕变特性共同作用的结果;新支护方案实施后,围岩位移、拱顶沉降以及收敛速率均出现显著降低,位移最终收敛并趋于稳定,工程应用效果良好;基于二次开发模型的数值模拟结果与工程实际监测数据高度吻合,验证了该模型在模拟隧道施工过程中围岩蠕变的合理性与准确性.该研究为类似富水蠕变地层中的隧道支护优化设计与长期稳定性评估提供了重要的理论依据与实践参考.

To address the issue of secondary lining cracking induced by creep of water-rich surrounding rock in the Yanglin Tunnel,this study employs an established hydro-mechanically coupled rock creep model and embeds it into numerical software for secondary development,enabling accurate simulation of the creep behavior of surround-ing rock in a water-rich environment.On this basis,by combining the convergence-confinement method with or-thogonal experiments,the influence of different support parameters on surrounding rock stability was systematically analyzed,thereby determining a new support scheme for the cracked section.Concurrently,field monitoring was carried out during the actual construction process,and key displacement and stress data were obtained.Finally,the programmed model was utilized to perform a hydro-mechanical coupled numerical simulation of the tunnel section under the new support scheme to evaluate its long-term stability.The results indicate that secondary lining crack-ing is not caused by a single factor but results from the synergistic effect of bias pressure from an inclined shale in-terlayer in the composite stratum and the creep behavior of carbonaceous mudstone.After implementing the new support scheme,surrounding rock displacement,crown settlement,and convergence rates decreased markedly,with displacements eventually converging to stable values,indicating satisfactory engineering performance.The numeri-cal simulation results based on the secondary development model are in good agreement with the actual field moni-toring data,confirming the validity and accuracy of the model in simulating surrounding rock creep during tunnel construction.This study provides an important theoretical basis and practical reference for the optimization of tun-nel support and long-term stability assessment in similar water-rich creeping strata.

于明圆;刘耀儒;黄跃群;谢穆武;张琪;武超

清华大学 水圈科学与水利工程全国重点实验室,北京 100084||中国人民警察大学 防火工程学院,河北 廊坊 065000清华大学 水圈科学与水利工程全国重点实验室,北京 100084清华大学 水圈科学与水利工程全国重点实验室,北京 100084||湖南省水利发展投资有限公司,湖南 长沙 410007湖南省水利水电勘测设计规划研究总院有限公司,湖南 长沙 410007清华大学 水圈科学与水利工程全国重点实验室,北京 100084清华大学 水圈科学与水利工程全国重点实验室,北京 100084

建筑与水利

复合地层断面水岩耦合蠕变特性支护优化收敛-约束法二次开发

composite stratum sectionhydro-mechanical couplingcreep characteristicsupport optimizationconvergence-confinement methodsecondary development

《华南理工大学学报(自然科学版)》 2026 (9)

163-175,13

国家自然科学基金项目(52179105)中国人民警察大学中央高校基本科研业务费专项资金项目(BSKYZX202543)犬木塘水库工程科技创新项目 Supported by the National Natural Science Foundation of China(52179105)

10.12141/j.issn.1000-565X.250428

评论