Study on Pilot Test of Vertical Mill for Regrinding of Classifier Sands of Tin-copper Associated Ore

中文摘要英文摘要

针对云南某锡铜共生矿选矿厂现有磨矿流程返砂量大、球磨机负荷过高、锡石易过磨,制约选矿厂处理能力提升与选别指标优化的行业共性问题,采用KLM-75型立式螺旋搅拌磨机开展返砂再磨半工业试验,系统考察介质充填率、设备处理量、磨矿浓度等核心工艺参数对磨矿效率、产品粒度分布及能耗的影响规律,通过多条件对比试验明确最优运行参数区间.研究结果表明,立磨机采用25 mm与30 mm混合钢球为研磨介质,在介质充填率30%~35%、处理量11~12.5 t/h的工况条件下,磨矿产品中-0.074 mm粒级产率满足≥40%的工艺要求,-0.01 mm过磨粒级产率可控制在10%以内,吨磨矿能耗约4.5 kW·h/t,实现了铜矿物单体解离与锡石过磨防控的双重目标.本文验证了立磨机应用于锡铜共生矿返砂再磨作业的技术可行性,可为该选矿厂磨矿系统扩能技改提供直接的参数支撑,也为同类复杂共伴生金属矿的磨矿工艺优化提供了参考范例.

Aiming at the common industrial problems existing in the concentrator of a tin-copper associated ore mine in Yunnan,such as large circulating load,excessive ball mill load and easy overgrinding of cassiterite,which restrict the improvement of concentrator throughput and the optimization of separation indexes,semi-industrial tests on regrinding of circulating sands were carried out using KLM-75 vertical spiral stirred mill.The influences of key process parameters including media filling ratio,equipment throughput and grinding concentration on grinding efficiency,product particle size distribution and energy consumption were systematically investigated,and the optimal operating parameter ranges were determined through multi-condition comparative tests.The research results show that when the vertical mill adopts mixed steel balls of 25 mm and 30 mm as grinding media,under the operating conditions of media filling ratio of 30%~35%and throughput of 11~12.5 t/h,the yield of the-0.074 mm size fraction in grinding products meets the process requirement of ≥40%,and the yield of the overground-0.01 mm size fraction can be controlled within 10%.The unit grinding energy consumption is as low as approximately 4.5 kW·h/t,realizing the dual goals of monomer dissociation of copper minerals and prevention and control of cassiterite overgrinding.This study confirms the technical feasibility and economic superiority of vertical mills for circulating sand regrinding of tin-copper associated ore.The research findings can offer direct parameter support for capacity expansion and technical renovation of the concentrator's grinding system,and provide a reference case for optimizing grinding flowsheets of similar complex associated metallic ores.

矣建林;柳彦昊;陶云肖;侯孝安

云南锡业股份有限公司大屯锡矿,云南个旧 661021昆明理工大学国土资源工程学院,云南 昆明 650093云南锡业股份有限公司大屯锡矿,云南个旧 661021北矿机电科技有限责任公司,北京 100160

矿业与冶金

立磨机锡铜共生矿半工业试验磨矿效率能耗

vertical milltin-copper associated orepilot testgrinding efficiencyenergy consumption

《云南冶金》 2026 (4)

49-53,72,6

云南省创新引导与科技型企业培育计划—科技揭榜制专项(202504BW050001)