Study on Application of Combined Cut-and Fill Mining Method with Delayed Backfilling for Deep Ore Bodies with Variable Thickness from Thin to Thick
针对凉山矿业落凼矿区深部薄变厚矿体开采中点柱式上向水平分层充填法适应性差、效率低、安全隐患大等问题,开展了点柱式上向水平分层充填法向分段空场嗣后充填法转型的应用研究.构建了"下部薄层点柱法加上部厚层分段空场嗣后充填法"的组合式采矿方法,形成"薄层控贫化回采—充填固结形成人工承载底板—厚层高效回采"的一体化开采体系;提出点柱法的适用边界(厚度<8m、深度<500 m、产能<300 t/d)、转型判断依据(厚度>10 m、深度>500 m、产能需求>500 t/d)和关键参数(充填体强度7d≥2MPa、养护周期7~9 d);揭示了"以充填体替代点柱构建人工顶板"的核心机制.工程实践表明:贫化率由10.61%降至4.37%,损失率由19.12%降至16.2%,发包成本降低约30%,供矿能力由200 t/d提升至800~1 000 t/d.研究成果可为深部复杂矿体的采矿方法优化提供工程借鉴.
Aiming at the problems such as poor adaptability,low efficiency and prominent potential safety hazards of the point-pillar upward horizontal cut-and-fill mining method applied to the mining of deep thin-to-thick variable ore bodies in Luodang Mining Area of Liangshan Mining Industry,an application research on the transformation from point-pillar upward horizontal cut-and-fill mining method to sublevel open stoping with delayed backfilling was carried out.A combined mining method adopting the"point-pillar mining for lower thin ore bodies and sublevel open stoping with delayed backfilling for upper thick ore bodies"scheme was constructed,forming an integrated mining framework featuring"low-dilution extraction of thin seams,formation of artificial load-bearing floors via consolidated backfilling,and high-efficiency extraction of thick seams".The applicable boundaries of the point-pillar mining method(ore body thickness<8 m,mining depth<500 m,production capacity<300 t/d),transformation judgment criteria(ore body thickness>10 m,mining depth>500 m,required production capacity>500 t/d)and key technical parameters(7-d backfill strength≥2 MPa,curing period of 7~9 d)were proposed.The core mechanism of"replacing point pillars with backfill bodies to construct artificial roof"was revealed.Engineering practice results show that The dilution rate fell from 10.61%to 4.37%,the ore loss rate decreased from 19.12%to 16.2%,the contract-awarding cost was reduced by about 30%,and the ore supply capacity was raised from 200 t/d to 800~1000 t/d.The research findings can offer engineering references for optimizing mining methods of deep complex ore bodies.
周朝兰;邹竹能;李明洁;杜海瑞;吴山西
昆明冶金研究院有限公司,云南 昆明 650031凉山矿业股份有限公司,四川会理 615146昆明冶金研究院有限公司,云南 昆明 650031昆明冶金研究院有限公司,云南 昆明 650031昆明冶金研究院有限公司,云南 昆明 650031
矿业与冶金
深部薄变厚矿体点柱式上向水平分层充填分段空场嗣后充填组合式采矿适用边界
deep thin-to-thick variable ore bodiespoint-pillar upward horizontal cut-and-fill miningsublevel open stoping with delayed backfillingcombined mining methodapplicable boundary
《云南冶金》 2026 (4)
43-48,6