复杂环境钢-混组合梁斜拉桥主梁拼装施工研究OA
Study on Main Girder Assembly Construction of Steel-Concrete Composite Girder Cable-stayed Bridge Under Complex Environment
甬江特大桥为三塔不对称钢-混组合梁斜拉桥,跨径布置为(50+275+540+570+214+81)m.受危化品港区等特殊环境限制,钢-混组合梁施工常用的节段整体吊装工法无法实施,因此采用80 t回转吊机对主梁构件进行了散拼;同时为在台风季到来前实现全桥合龙,在常规"2节段1循环"施工方法基础上,提出了吊机滞后前移、边主梁预偏转安装的施工工艺.为验证施工方案的可行性,采用ANSYS软件建立了主梁节段三维有限元模型,模拟分析了吊装施工过程中结构的应力与变形状态.计算结果表明:在整个拼装过程中,主梁钢结构与混凝土桥面板的应力均处于安全范围内;边主梁在结构自重与吊装荷载作用下会产生扭转变形,且该变形会向悬臂前端传递并累积.通过将吊机适当远离悬臂端部,并预设边主梁1.5 mm反向偏转的措施,可有效减小扭转变形累积,保障横梁顺利拼接.工程实践表明,采用"2节段1循环"施工方案,既提高了主梁施工效率,也为复杂环境下同类型桥梁的施工提供了有益参考.
The Yongjiang Extra Large Bridge is a three-tower asymmetric cable-stayed bridge with steel-concrete composite girders,and its span arrangement is(50+275+540+570+214+81)m.Restricted by special environments such as the hazardous chemical port area,the integral segment hoisting method commonly adopted for the construc-tion of steel-concrete composite girders cannot be implemented.Therefore,an 80 t slewing crane was used for piece-by-piece assembly of the main girder components.Meanwhile,to achieve the full-bridge closure before the arrival of typhoon season,a construction technology featuring delayed forward movement of the crane and pre-de-flection installation of side main girders was proposed on the basis of the conventional"two segments per cycle"construction method.To verify the feasibility of the construction scheme,ANSYS software was adopted to establish a three-dimensional finite element model of main girder segments,and the structural stress and deformation during hoisting construction were simulated and analyzed.The calculation results show that the stresses of the steel struc-ture of the main girder and concrete bridge deck remain within the safe range throughout the assembly process.The side main girders undergo torsional deformation under the action of self-weight and hoisting loads,and such defor-mation transmits to the cantilever front end and accumulates.Appropriately keeping the crane away from the can-tilever end and presetting a reverse deflection of 1.5 mm for the side main girders can effectively reduce the accumu-lation of torsional deformation and ensure smooth splicing of cross beams.Engineering practice demonstrates that the"two segments per cycle"construction scheme improves the construction efficiency of the main girder and provides valuable reference for the construction of similar bridges under complex environments.
刘徐光;李凯;赵志杰;李泽桐;汤陈皓
浙江宁波杭甬复线三期高速公路有限公司,浙江宁波 315800浙江宁波杭甬复线三期高速公路有限公司,浙江宁波 315800浙江交工集团股份有限公司,浙江 杭州 310051浙江交工集团股份有限公司,浙江 杭州 310051浙江交工集团股份有限公司,浙江 杭州 310051
交通工程
三塔不对称斜拉桥钢-混组合梁回转吊机节段吊装施工构件散拼数值模拟
three-tower asymmetric cable-stayed bridgesteel-concrete composite girderslewing cranesegment hoisting constructionpiece-by-piece component assemblynumerical simulation
《市政技术》 2026 (9)
72-78,88,8