首页|期刊导航|山东煤炭科技|工作面开采覆岩破坏高度预计分析及防砂煤(岩)柱尺寸确定

工作面开采覆岩破坏高度预计分析及防砂煤(岩)柱尺寸确定OA

Prediction Analysis of Overburden Rock Failure Height and Size Determination of Sand Control Coal(Rock)Pillar in Working Face Mining

中文摘要英文摘要

针对高庄煤业 33下06工作面处于第四系厚松散层-薄基岩条件下的防砂防水问题,综合采用覆岩"两带"预测公式及 3下301工作面实测数据,分析采高 3.0~4.6 m条件下 3下煤覆岩垮落带和导水裂缝带发育高度.结果显示,第四系下组下段含水层富水性弱,基岩风化带隔水性能良好,对工作面基本不构成充水(砂)威胁;不同采高下垮落带高度约 16.69~43.61 m、导水裂缝带高度约 41.4~59.8 m,计入 20 m基岩风化含水层带深度后,防砂煤(岩)柱最小高度为 46~78 m.工作面采高应根据 3上煤层采动范围和局部基岩厚度分区确定,基岩厚度不满足相应煤(岩)柱留设要求的区段应降低采高或留设保护煤体.综合考虑近距离煤层重复采动、覆岩破坏高度及基岩风化含水层带深度,可为类似厚松散层-薄基岩条件下防砂煤(岩)柱留设与采高确定提供参考.

Aiming at the sand control and water prevention problems of the 33lower06 working face in Gaozhuang Coal Industry,which was located in the Quaternary thick loose layer-thin bedrock condition,the"two zones"prediction formula of overburden rock and the actual measured data of the 3lower301 working face were comprehensively adopted to analyze the development heights of the overburden rock collapse zone and water conducting fissure zone in the 3lower coal under the condition of mining height of 3.0-4.6 m.The results indicate that the water richness of aquifers in the lower section of the Quaternary Lower Group was weak,and the water isolation property of the bedrock weathering zone was good,which basically doesn't pose a water(sand)threat to the working face;The collapse zone heights under different mining heights were about 16.69-43.61 m,and the heights of water conducting fissure zone were about 41.4-59.8 m.After taking into account the 20 m depth bedrock weathered aquifer zone,the minimum height of the sand control coal(rock)pillar was 46-78 m.The working face mining height should be determined by zoning according to the mining range of the 3upper coal seam and the local bedrock thickness.In sections where the bedrock thickness doesn't meet the corresponding coal(rock)pillar retention requirements,the mining height should be reduced or protective coal bodies should be retained.This comprehensively considering the close distance coal seam repeated mining,the overburden rock failure height,and the depth of the weathered aquifer zone of the bedrock,can provide reference for the sand control coal(rock)pillar retention and mining height determination under similar thick loose layer-thin bedrock conditions.

马坡;赵克刚;何承贵

枣庄矿业集团高庄煤业有限公司,山东 济宁 277605枣庄矿业集团高庄煤业有限公司,山东 济宁 277605枣庄矿业集团高庄煤业有限公司,山东 济宁 277605

矿业与冶金

防砂煤柱覆岩破坏高度采高条件工作面地质条件安全开采

sand control coal pillaroverburden rock failure heightmining height conditionworking face geological conditionsafety mining

《山东煤炭科技》 2026 (8)

5-11,7

10.3969/j.issn.1005-2801.2026.08.002