运营地铁高架车站改扩建不停运施工与沉降控制技术OA

Construction Without Service Interruption and Settlement Control Techniques for Expansion and Renovation of Operating Elevated Metro Stations

中文摘要英文摘要

早期建设的地铁高架车站因客流增长需改扩建,且需保障线路不停运,施工组织与新老结构差异沉降控制为核心难题.以南京地铁2号线马群站改扩建工程为实例,通过分区流水施工组织优化、三维仿真预判沉降、动态监测闭环管控,实现不停运施工以及施工全过程安全可控、既有线路正常运营的目标.车站新增建筑面积7 735 m2,服务能力大幅提升.研究成果均为落地性强的工程实用技术,可直接用于同类运营地铁高架车站改扩建项目.

Early-built elevated metro stations often require expansion and renovation due to increasing passenger flow,while maintaining uninterrupted operation poses significant challenges.The core difficulties lie in construction organization and controlling differential settlement between new and existing structures.Taking the expansion pro-ject of Maqun Station on Nanjing Metro Line 2 as a case study,this paper presents practical solutions including op-timized zoned flow construction organization,three-dimensional simulation for settlement prediction,and dynamic monitoring with closed-loop control.These measures successfully achieved non-stop construction,ensured safety throughout the construction process,and maintained normal operation of the existing line.The station's newly added floor area reaches 7 735 m2,significantly enhancing its service capacity.The research outcomes are highly applicable engineering techniques that can be directly implemented in similar expansion and renovation projects of operating elevated metro stations.

谢渭平

中国水利水电第八工程局有限公司,湖南长沙 410004

交通工程

运营地铁高架车站改扩建不停运施工数值模拟

operating metroelevated stationexpansion and renovationconstruction without service interruptionnumerical simulation

《市政技术》 2026 (8)

160-167,182,9

10.19922/j.1009-7767.2026.08.160