浅谈硬梁包地下厂房混凝土高效施工技术OA

Brief discussion on high-efficiency concrete construction technology for underground powerhouse of Yingliangbao Hydropower Project

中文摘要英文摘要

硬梁包水电站地下厂房在开挖严重滞后的条件下,混凝土施工工期异常紧张.为保障发电目标,采取通道优化、入仓手段创新、关键路径缩短等核心的综合性技术与管理措施,最终在开挖工期滞后一百余天的情况下仍提前6 d完成首台机组浇筑至发电机层节点目标,质量和速度均远高于行业平均水平,证明了该措施的有效性,并为同类工程提供了借鉴.

Under the condition of severe excavation delays in the underground powerhouse of Yingliangbao Hy-dropower Station,the concrete construction schedule became extremely tight.To guarantee the power genera-tion target,a series of comprehensive technical and management measures were adopted,including access route optimization,concrete placement method innovation,and critical path compression.As a result,despite a delay of over 100 days in excavation work,the first unit was poured to the generator floor level six days ahead of the schedule.The quality and speed of construction outperformed the industry average,while safety and reliability were maintained.This demonstrates the effectiveness of the adopted measures and provides references for sim-ilar projects.

高强;陈洋;王雅儒;纳小平;郭映勇

中国水利水电第五工程局有限公司,四川 成都 610000中国水利水电第五工程局有限公司,四川 成都 610000中国水利水电建设工程咨询中南有限公司,湖南 长沙 410000中国水利水电第五工程局有限公司,四川 成都 610000中国水利水电第五工程局有限公司,四川 成都 610000

建筑与水利

硬梁包水电站地下厂房混凝土高效施工

Yingliangbao Hydropower Projectunderground powerhouse concretehigh-efficiency construction

《四川水力发电》 2026 (4)

87-91,5

10.20196/j.cnki.scslfd.20260418

评论