马坑铁矿属于顶板直接充水的岩溶大水矿床,矿坑涌水量大,属于水文地质条件中等—偏复杂的岩溶充水矿床.随着 0m以下采选扩能的推进,急需开展深部水文地质工作,特别是深部涌水量预测,作为后续掘进计划、排水设施设备选型的依据.本文通过水文地质比拟法预测 0m以下开采涌水量,以此作为矿山疏干研究设计的依据之一;同时,指导深部探放水工作,保障深部开采安全.

Makeng Iron Mine is a karst water-rich mining area with direct roof water inflow,featuring large mine water inflow and a moderate to relatively complex hydrogeological condition as a karst water-bearing deposit.With the advancement of the mining and beneficiation capacity expansion project below the 0 m elevation,the water inflow risk in deep mining has significantly increased,making it urgent to carry out special hydrogeological research.This paper adopts the hydrogeological analogy method,combined with the hydrogeological data of the shallow mined areas in the mine,to predict the mine water inflow in the mining area below the 0m elevation.The research results can serve as one of the bases for the special research and design of mine dewatering,and simultaneously guide the deep water exploration and drainage work to ensure the safety of deep mining.

金其忠

福建马坑矿业股份有限公司,福建 龙岩 364000

水位地质比拟法涌水量富水性

hydrogeological analogy methodmine water inflowwater richness

《福建冶金》 2026 (5)

1-3,3