船闸立面大块条石干挂安装技术优化研究OA

Optimization on Dry-Hang Installation Technology for Large-Scale Dressed Stone Facades in Ship Locks

中文摘要英文摘要

北运河木厂船闸工程立面条石防护采用干挂法施工,但传统安装工艺存在施工效率偏低、工期风险较大等问题.通过技术诊断,明确沟槽与挂件的对位校准为制约施工效率的关键瓶颈工序.针对这一问题,提出2项核心技术改进措施:①更换吊具材质,采用直径8 mm软钢丝绳(6×7-FC1770ZS)替代传统吊绳,以解决安装后吊具撤除困难的问题;②优化测量基准,将量测部位由条石正面调整为无花纹造型的背面,以提高测量精度.工程应用结果表明,优化后单块条石安装时间由36 min缩短至14 min,降幅达61.1%,日安装量由17块提高至41块,满足了节点工期要求.研究成果可为同类船闸及水利工程条石安装施工提供参考.

The facade stone protection of the Muchang Ship Lock Project on the North Canal was constructed using the dry-hang method.However,the conventional installation process suffered from issues such as relatively low construction efficiency and significant schedule risks.Through technical diagnosis,the alignment calibration between the grooves and the hangers was identified as the key bottleneck restricting construction efficiency.To address this problem,two core technical improvement measures were proposed:(1)replacing the sling material with a soft steel wire rope(6×7-FC1770ZS)of 8 mm diameter to resolve the difficulty of sling removal after installation;and(2)optimizing the measurement reference by shifting the measuring points from the front face of the dressed stone to the back face without decorative patterns,thereby improving measurement accuracy.Engineering application results demonstrate that after optimization,the installation time per single block of dressed stone was reduced from 36 minutes to 14 minutes,a reduction of 61.1%,and the daily installation volume increased from 17 blocks to 41 blocks,meeting the milestone schedule requirements.The research findings can serve as a reference for the installation of dressed stones in similar ship lock and water conservancy projects.

霍晓峰

华北水利水电工程集团有限公司,天津 300000

建筑与水利

船闸工程干挂法条石安装施工技术工效优化技术经济

ship lock projectdry-hang methoddressed stone installationconstruction technologywork efficiency optimizationtechnical economy

《海河水利》 2026 (z1)

159-162,194,5

10.3969/j.issn.1004-7328.2026.增刊1.029