西津泵站边坡支护方式比选OA
Comparison and selection of slope support methods for Xijin Pump Station
针对环北部湾广西水资源配置工程西津泵站工程区永久边坡稳定性不足的问题,基于地质勘察与边坡稳定分析成果,比较了桩基支护与全断面开挖两种支护方案.通过建立典型计算断面,采用简化毕肖普法对自然边坡及开挖支护后边坡进行多工况稳定性验算,并在工程投资、施工便捷性及环保效益等方面进行了对比分析,为西津泵站基坑边坡开挖方案的确定提供依据.
To address the inadequate stability of the permanent slope in the project area of Xijin Pump Station,a component of Guangxi Water Resources Allocation Project around Beibu Gulf,based on the results of geological in-vestigation and slope stability analysis,two support schemes,namely pile foundation support and full-section exca-vation,were compared.By establishing typical calculation sections,the simplified Bishop method was adopted to conduct stability calculations under multiple working conditions for both the natural slopes and the slopes after ex-cavation and support.Comparative analysis was conducted in terms of engineering investment,construction conve-nience and environmental protection benefits,providing a basis for determining the excavation scheme of the foun-dation pit slope of Xijin Pump Station.
苏宏宽;刘时明
广西水利电力勘测设计研究院有限责任公司,南宁 530023广西水利电力勘测设计研究院有限责任公司,南宁 530023
天文与地球科学
边坡支护比选抗滑稳定桩基支护全断面开挖西津泵站环北广西工程
comparison and selection of slope support methodsanti-sliding stabilitypile foundation supportfull-section excavationXijin Pump StationGuangxi Water Resources Allocation Project around Beibu Gulf
《广西水利水电》 2026 (4)
59-63,5
评论