一起500kV GIS内部机械运动部件缺陷引起的局部放电分析OA

Partial Discharge Analysis Caused by Internal Mechanical Moving Parts Defects in 500 kV GIS

中文摘要英文摘要

针对某500 kV变电站气体绝缘金属全封闭组合电器(gas insulated switchgear,GIS)断路器局部放电异常缺陷,采用超声波+特高频法开展现场带电检测与定位,通过X射线进行缺陷验证,利用视频内窥镜检查异物分布,使用扫描电子显微镜结合能谱仪对异物进行成分分析,结合返厂全流程解体检查,溯源异物源头并分析缺陷成因.本次局部放电异常直接原因为GIS内部机械运动部件缺陷造成异物积累导致电场畸变,根本原因为设备设计缺陷与生产工艺管控不到位导致异物持续积累,最终引发局部放电,并提出设备整改、专项排查、强化监测、工艺优化四位一体的处理与运维防控措施,为同类型设备故障排查提供技术参考.

In response to the abnormal partial discharge defect of the gas insulated switchgear(GIS)circuit breaker in a 500 kV substation,ultrasonic and ultra-high frequency(UHF)methods are used for on-site live detection and positioning,while X-ray is adopted for defect verification.The video endoscope is employed to examine the distribution of foreign matters,and the scanning electron microscope(SEM)combined with energy dispersive spectrometer(EDS)is applied for component analysis.Combined with the full-process disassembly inspection after returning to the factory,the source of foreign matters is traced and the causes of defects are analyzed.The direct cause of the abnormal partial discharge is electric field distortion caused by foreign matter accumulation resulting from defects in internal mechanical moving parts of the GIS.The root cause is continuous foreign matter accumulation due to equipment design deficiencies and inadequate production process control,which ultimately leading to partial discharge.A four-in-one strategy incorporating equipment rectification,specialized inspection,enhanced monitoring,and process optimization is proposed for treatment,operation and maintenance prevention and control,providing a technical reference for fault diagnosis of similar equipment.

凌应河;李玉杰;张照辉;朱润卿;冯侨钧

南京宁众人力资源咨询服务有限公司,南京 210000国网江苏省电力有限公司电力科学研究院,南京 210000国网江苏省电力有限公司电力科学研究院,南京 210000国网江苏省电力有限公司电力科学研究院,南京 210000南京宁众人力资源咨询服务有限公司,南京 210000

信息技术与安全科学

GIS断路器局部放电X射线解体分析工艺缺陷

GIS circuit-breakerpartial discharge(PD)X-raydisassembly analysisprocess defect

《内蒙古电力技术》 2026 (3)

88-97,10

10.19929/j.cnki.nmgdljs.2026.0036