首页|期刊导航|广西水利水电|小峰水库大坝旋挖桩基础处理

小峰水库大坝旋挖桩基础处理OA

Foundation treatment with rotary drilling pile for main dam of Xiaofeng Reservoir

中文摘要英文摘要

土石坝在长期运行过程中易出现坝基渗漏、沉降等问题,基础加固是提升大坝安全性的关键措施.旋挖灌注桩因其施工效率高、成孔质量好,被广泛应用于水利除险加固工程.然而,在复杂地质条件下,坝基中存在的孤石对成孔效率与成桩质量构成严重干扰.本文以小峰水库除险加固项目为例,系统介绍了孤石的分布特征、对施工的影响及应对措施.通过补充钻探、试桩验证与风险分区,实现对孤石的预判识别;结合孤石尺寸与位置,采取截齿钻进、冲击破碎、二次清孔等针对性施工工艺,并通过全过程质量控制保障成桩质量.项目中38根遇到孤石的桩全部顺利成桩,成桩合格率98%以上.结果表明,合理的孤石处理技术与成孔参数控制体系可显著提升复杂地基条件下旋挖桩施工的安全性与可控性.

Earth-rock dams are prone to issues such as foundation leakage and settlement during long-term opera-tion,making foundation reinforcement a crucial measure for enhancing dam safety.Rotary drilling cast-in-place piles,renowned for high construction efficiency and excellent hole-forming quality,have been widely adopted in hy-draulic reinforcement projects.However,under complex geological conditions,the presence of isolated boulders in dam foundations significantly interferes with both hole-forming efficiency and pile quality.Taking the Xiaofeng Res-ervoir Reinforcement Project as an example,a systematic introduction is made on the distribution characteristics of isolated boulders,the impact on construction,and corresponding measures.Through supplementary drilling,trial pile verification,and risk zoning,the pre-identification of isolated boulders was achieved.Based on the sizes and lo-cations of isolated boulders,targeted construction techniques such as toothed drilling,impact crushing,and second-ary hole cleaning were adopted,with full-process quality control to ensure pile integrity.All 38 piles encountering isolated boulders in the project were successfully completed,with a qualification rate exceeding 98%.The results demonstrate that rational isolated boulder treatment techniques combined with hole-forming parameters control sys-tem can significantly improve the safety and controllability of rotary drilling pile construction under complex founda-tion conditions.

杨川

广西水利电力勘测设计研究院有限责任公司,南宁 530023

建筑与水利

土石坝旋挖灌注桩孤石处理基础加固清孔灌注质量控制小峰水库

earth-rock damrotary drilling cast-in-place pilesisolated boulder treatmentfoundation reinforce-mentquality control of hole cleaning and castingXiaofeng Reservoir

《广西水利水电》 2026 (3)

51-55,5