钢管混凝土拱桥封铰混凝土浇筑时机对比研究OA
Comparative Study on Pouring Timing of Sealing Hinge Concrete for Concrete-Filled Steel Tube Arch Bridge
钢管混凝土拱桥封浇混凝土浇筑时机直接影响施工工期及拱肋受力状态.为明确不同浇筑时机的结构响应差异,该文以广西平岑高速北流河特大桥为工程背景,采用Midas Civil建立其有限元模型,对比分析了以下4种封铰混凝土浇筑时机:封铰钢管对焊后;拱肋合龙后、管内混凝土浇筑前;管内混凝土浇筑后、格子梁吊装前;桥面板湿接缝浇筑后、二期恒载施加前.通过施工全过程有限元仿真分析,比较了4种时机下各关键部位的内力、应力、变形及成桥阶段的变形.结果表明:4种封铰混凝土浇筑时机均是可取的;从拱脚处弦管的强度及稳定性看,时机4(桥面板湿接缝浇筑后再浇筑封铰混凝土)最有利.只要不存在工作面冲突,封铰钢管对焊后的任何施工阶段均可进行封铰混凝土浇筑,产生上述现象的原因是该桥拱肋轴线为悬链线,恒载状态以受压为主,弯矩较小.研究成果为该桥封铰混凝土浇筑时机的选择提供了依据,可为类似桥梁相关施工提供参考.
The pouring timing of sealing hinge concrete for concrete-filled steel tube arch bridges directly affects the construction duration and the stress state of arch ribs.To clarify the structural response differences at different pouring timings,the Beiliuhe Extra-large Bridge on the Pingxi-Cenxi Expressway in Guangxi Province was taken as the engineering background in this paper.A finite element model was established using Midas Civil,and the following four pouring timings of sealing hinge concrete were comparatively analyzed:immediately after the butt welding of sealing hinge steel pipes;after the closure of arch ribs and before the pouring of concrete inside pipes;after the pouring of concrete inside pipes and before the lifting of lattice girders;after the pouring of wet joints of the bridge deck and before the application of the second-phase dead load.Through the finite element simulation analysis of the whole construction process,the internal forces,stresses,and deformations of key parts under the four timings,as well as the deformations at the completed bridge stage,were compared.The results indicate that all four pouring timings of sealing hinge concrete are feasible;from the perspective of the strength and stability of chord pipes at the arch feet,timing 4(pouring the sealing hinge concrete after the pouring of wet joints of the bridge deck)is the most favorable.As long as there is no conflict in working surfaces,the pouring of sealing hinge concrete can be carried out at any construction stage after the butt welding of sealing hinge steel pipes.The reason for the above phenomenon is that the arch rib axis of this bridge is a catenary curve,which is mainly subjected to compression with a small bending moment under the dead load state.The research results provide a basis for selecting the pouring timing of sealing hinge concrete for this bridge and can serve as a reference for related construction of similar bridges.
王晓亮;付凯歌;张松;王中强;陈卓异
中交二公局第五工程有限公司,陕西 西安 710119中交二公局第五工程有限公司,陕西 西安 710119中交二公局第五工程有限公司,陕西 西安 710119长沙理工大学 土木与环境工程学院,湖南 长沙 410114长沙理工大学 土木与环境工程学院,湖南 长沙 410114
交通工程
钢管混凝土拱桥封铰混凝土浇筑时机有限元仿真分析
concrete-filled steel tube arch bridgesealing hinge concretepouring timingfinite element simulation analysis
《中外公路》 2026 (3)
142-149,8
国家自然科学基金资助项目(编号:52478129)湖南省教育厅重点项目(编号:23A0248)
评论