盾构穿越富水砂层对高铁桥梁桩基变形规律的影响分析OA
Analysis of the impact of shield tunneling through water-rich sand layer on the deformation pattern of high-speed railway bridge pile foundations
盾构近距离穿越高铁桥梁桩基时,对土体的扰动会引起桩基偏移,进而对上方高铁的安全运行构成潜在威胁.为探究富水砂层盾构施工对邻近桩基变形的影响规律,以郑州地铁12号线下穿京广高铁桥梁工程为依托,首先探讨了盾构机推力和动力作用下桩基的失稳机理,继而通过Abaqus软件建立了隧道-土体-桩基有限元模型,采用"生死单元法"模拟了双线隧道盾构开挖全过程,并结合施工监测数据,分析了桩基在盾构单双线掘进条件下不同方向上的偏移情况.结果表明:①在该下穿案例中,盾构机可安全通过施工区域,且桩基变形均处于国家标准控制范围之内.②盾构机的推力使桩身朝掘进方向偏移,当盾构机到达桩基平面时,偏移速率达到最大,此后速率减小并伴有位移回弹.③桩基受盾构机横向挤压,朝背离隧道方向偏移,又受后行隧道盾构机挤压而往回偏移,最终朝后行隧道方向偏移并趋于稳定;桩身最大竖向位移发生在中上部,下部因土层卸载回弹导致沉降值最小.④单线隧道的地表沉降曲线呈"V"形,双线隧道呈"W"形,最大沉降值发生在各隧道中轴线处,且后行隧道最大沉降值小于先行隧道.经数据比对,模型结果与监测数据吻合较好.该研究成果可为富水砂层地区地铁盾构近距离下穿高铁桥梁桩基的施工控制、变形分析及安全保障提供理论依据和工程参考.
When a shield tunnel traverses the pile foundation of the high-speed railway bridge at a close distance,the disturbance of the soil will cause the pile foundation to offset,posing a potential threat to the safe operation of the high-speed railway overhead.To explore the deformation rule of adjacent pile foundations caused by shield construction in a water-rich sand layer,based on the case of Zhengzhou Metro Line 12 underpassing the Beijing-Guangzhou High-speed Railway bridge,this paper first discusses the instability mechanism of the pile foundation under the thrust and dynamic action of the shield tunneling machine,and then establishes a tunnel-soil-pile foundation finite element model using Abaqus.The whole process of shield excavation of the double-line tunnel is simulated by the"birth-death element method",and the deviation of the pile foundation in different directions under the conditions of single-and double-line tunneling is analyzed based on construction monitoring data.The following conclusions are drawn:①In this construction case,the shield machine can safely pass through the construction area,and the deformation of the pile foundation is within the control range of national standards.②The thrust of the shield machine causes the pile body to shift toward the driving direction.When the shield machine reaches the pile foundation plane,the migration rate reaches its maximum,and then the rate decreases with displacement rebound.③The pile foundation is offset away from the tunnel by the lateral extrusion of the shield tunneling machine,and then offset back by the extrusion of the rear shield tunneling machine.Finally,the pile foundation is stable in the direction toward the rear tunnel.The maximum vertical displacement of the pile body occurs in the middle and upper parts,and the settlement of the lower part is the smallest due to the rebound from soil unloading.④The surface settlement curve for the single line is"V"shaped,and that for the double line is"W"shaped.The maximum settlement value occurs on the central axis of each tunnel,and the maximum settlement amount of the rear line is less than that of the advance line.After data comparison,the model results are well validated with the monitoring data.The research results of this study can provide theoretical basis and engineering references for the construction control,deformation analysis and safety guarantee of subway shield tunneling passing close to the bridge pile foundation of high-speed railway in areas with abundant water-bearing sand layers.
聂承庆;汪先国;海洋;杭超超;王晓睿
中铁十一局集团有限公司,湖北 武汉 430061||城市地下交通工程防灾减灾河南省交通运输行业技术创新中心,河南 郑州 450046中铁十一局集团有限公司,湖北 武汉 430061郑州交通发展投资集团有限公司,河南 郑州 450047城市地下交通工程防灾减灾河南省交通运输行业技术创新中心,河南 郑州 450046||华北水利水电大学地球科学与工程学院,河南 郑州 450046城市地下交通工程防灾减灾河南省交通运输行业技术创新中心,河南 郑州 450046||华北水利水电大学地球科学与工程学院,河南 郑州 450046
资源环境
富水砂层盾构掘进地表沉降高铁桥梁桩基变形监测数据
water-rich sand layershield tunnelingsurface settlementhigh-speed railway bridgepile foundation deformationmonitoring data