基于轻量化模型的自动切分技术及进度管理应用研究OA
Automatic Segmentation of Lightweight Models and Its Application to Construction Schedule Management
为解决多学科交叉工程应用中施工进度精细化管理难题,降低BIM 技术对传统设计软件的依赖,文章提出了一种基于轻量化模型自动切分与施工进度动态双向反馈方法.该方法以项目施工数据与设计模型为基础,突破了模型自动切分与进度数据实时交互的技术瓶颈.依托大石峡水利枢纽工程的实践应用,实现了BIM 设计模型在 Web端的自动切分及参数化施工数据集成,显著提升BIM 模型与施工数据之间的双向驱动效率.实践表明,该方法能够为工程项目进度管理提供精准的可视化模型支撑,有效推动施工管理向数字化与智能化转型,对同类大型工程具有重要参考价值.
In order to solve the problem of fine management of construction progress in interdisciplinary engineering applications and reduce the dependence of BIM technology on traditional design software,this paper proposes a method based on automatic segmentation of lightweight model and dynamic two-way feedback of construction progress.Based on construction data and design model,this method breaks through the technical bottleneck of automatic model segmentation and real-time interaction of schedule data.Relying on the practical application of Dashixia water conservancy project,the automatic segmentation of BIM design model on the Web and the integration of parametric construction data are realized,which significantly improves the bidirectional driving efficiency between BIM model and construction data.Practice shows that this method can provide accurate visual model support for engineering project schedule management,effectively promote the transformation of construction management to digital and intelligent,and has important reference value for similar large-scale projects.
宋晓建;徐宇涛;李建东;栗煜;邢洁鋆
中国葛洲坝集团股份有限公司,湖北 宜昌 443002中国电建集团西北勘测设计研究院有限公司,西安 710001新疆葛洲坝大石峡水利枢纽开发有限公司,新疆 阿克苏 843407中国电建集团西北勘测设计研究院有限公司,西安 710001||西安市清洁能源数字化技术重点实验室,西安 710001中国电建集团西北勘测设计研究院有限公司,西安 710001
建筑与水利
建筑信息模型技术进度管理数字化模型自动切分网页应用数据管理
building information modeling(BIM)schedule managementdigital transformationmodel segmentationweb applicationdata integration
《广东水利水电》 2026 (6)
104-110,7
国家重点研发计划项目(编号:2023YFF0905500)陕西省重点研发计划项目(编号:2024GX-YBXM-148).