首页|期刊导航|中国水利水电科学研究院学报(中英文)|基于数值模拟的山前蓄滞洪区减灾成效量化分析与评估

基于数值模拟的山前蓄滞洪区减灾成效量化分析与评估OA

Quantitative analysis and evaluation of disaster reduction effectiveness of flood storage and detention areas based on numerical simulation

中文摘要英文摘要

山区河道洪水严重威胁山前建成区安全,通过山前建设蓄滞洪区,可蓄滞洪水、降低洪水流速、削减河道洪峰,有效缓解洪水对建成区的冲击.本研究以北京市温榆河流域北沙河为例,通过基于动力学原理的数值模拟方法,对山区河道洪水自由下泄情景以及经过蓄滞洪区调蓄后下泄情景分别进行洪水演进过程模拟计算,对比分析北沙河修建蓄滞洪区前后不同重现期洪水可能导致的洪水风险程度与分布,实现对蓄滞洪区防洪减灾成效的评估.分析结果认为:不同重现期洪水情景下,北沙河山前蓄滞洪区均能显著降低下游河道洪峰,减少河道两岸受淹面积与水深,降低区域洪水风险;整体减灾成效受蓄滞洪区规模制约,北沙河蓄滞洪区在20年一遇洪水情景下可达最高减灾效益,GDP损失减少率达27.55%,50年一遇设计洪水次之,为22.45%.利用洪涝过程数值模拟手段对蓄滞洪区等规划或在建防洪工程进行洪水情景分析,通过对比分析工程前后区域洪涝风险,可有效实现对工程减灾成效的量化分析与评估.

Mountain river floods pose a serious threat to the safety of foothill urban areas.Constructing flood deten-tion and storage zones in front of mountainous regions can retain floodwater,reduce flow velocity,attenuate flood peaks,and effectively mitigate the impact of floods on developed areas.Taking the Beisha River in the Wenyu River Basin,Beijing,as a case study,this research employs a numerical simulation method based on hydrodynamic prin-ciples to simulate the flood evolution processes under two scenarios:free flood discharge and discharge regulated by flood detention zones.By comparing the flood risks and spatial distributions under different return-period floods before and after the construction of detention zones,the effectiveness of flood control and disaster mitigation was evaluated.The results indicate that:under various return-period flood scenarios,the foothill detention zones along the Beisha River can significantly reduce downstream flood peaks,inundation extent,and water depth,thereby lowering regional flood risk;the overall mitigation effect is constrained by the scale of the detention zones—under the 20-year flood scenario,the Beisha River detention zone achieves the highest mitigation benefit,reducing GDP losses by 27.55%,followed by 22.45%under the 50-year design flood;numerical simulation of flood processes provides an effective means to quantitatively analyze and assess the mitigation performance of planned or ongoing flood control projects,through comparative analysis of flood risks before and after project implementation.

何欣航;郝晓丽;徐美;刘舒;胡丽楠;石树兰

中国水利水电科学研究院,北京 100038中国水利水电科学研究院,北京 100038中国水利水电科学研究院,北京 100038中国水利水电科学研究院,北京 100038北京市水务局,北京 101117北京市水文总站,北京 100089

建筑与水利

数值模拟洪涝灾害水文水动力模型蓄滞洪区减灾成效量化分析

numerical simulationflood and waterlogging disastershydrological-hydraulic modelflood storage and detention areaquantitative analysis of disaster mitigation effectiveness

《中国水利水电科学研究院学报(中英文)》 2026 (3)

357-368,12

国家重点研发计划项目(2023YFC3008502)

10.3724/j.jiwhr.20250173