TBM刀盘卡机风险分级预测方法构建与验证OA
Formulation and validation of a risk graded prediction method for TBM cutterhead jamming
针对TBM穿越断层破碎带时刀盘卡机灾害预测难题,收集整理了 TBM工程数据库,构建了关联掌子面最大变形与TBM最大驱动扭矩的卡机风险预测图,建立了考虑岩体强度与地应力比值的掌子面变形量预测模型,结合预测模型与预测图,形成了一套TBM刀盘卡机风险分级预测方法,并依托国内3个TBM工程对判别方法可靠性进行了验证.结果表明:针对刀盘卡机风险,可划分为极高风险、较高风险、中等风险、较低风险和极低风险五级等级;掌子面变形量预测模型中强度应力比与掌子面变形率呈负指数函数关系,基于模型可获取隧洞掌子面变形量;基于所提出的刀盘卡机风险分级预测方法的预测结果与工程实际相比总体准确率可达96%,可用于隧洞工程TBM刀盘卡机风险的判别.
To address the challenges of predicting the TBM cutterhead jamming risk during tunneling through fault zones,a TBM engineering database was compiled and analyzed.A risk prediction diagram for cutterhead jamming was developed by correlating the maximum tunnel face deformation with the TBM's maximum driving torque.A pre-dictive model for tunnel face deformation was established based on the ratio of rock strength to in-situ stress.By inte-grating this model with the risk diagram,a comprehensive method for assessing cutterhead jamming risk was formu-lated and validated using data from three TBM projects in China.The results demonstrate that:(1)the proposed risk diagram classifies jamming potential into five distinct levels:extremely high,high,medium,low,and very low.(2)The deformation prediction model reveals a negative exponential relationship between the strength-stress ratio and the tunnel face deformation rate,enabling quantitative deformation estimation based on the model.(3)The risk graded prediction method achieved an overall accuracy of 96%when validated against actual project data,demonstrating its applicability for jamming risk evaluation in TBM tunnel engineering.
陈天楠;刘立鹏;汪小刚;刘和艺;李佩茹
中国水利水电科学研究院 流域水循环与水安全全国重点实验室,北京 100038中国水利水电科学研究院 流域水循环与水安全全国重点实验室,北京 100038中国水利水电科学研究院 流域水循环与水安全全国重点实验室,北京 100038中国水利水电科学研究院 流域水循环与水安全全国重点实验室,北京 100038中国水利水电科学研究院 流域水循环与水安全全国重点实验室,北京 100038
建筑与水利
隧洞工程刀盘卡机风险预测数值模拟
tunnel engineeringcutterhead jammingrisk assessmentnumerical simulation
《水利学报》 2026 (4)
601-611,11