基于模糊综合评判法的某铀矿井开拓方案选择OA

Selection of Uranium Mine Well Development Plan Based on Fuzzy Comprehensive Evaluation Method

中文摘要英文摘要

矿井开拓方案选择是一个多因素、多指标的复杂过程.为了降低主观判断对矿井开拓方案选择的影响,以某铀矿井为研究对象,基于模糊数学理论建立了模糊综合评判模型,确定了 10项影响因素的模糊权重,量化了开拓方案的影响程度.在模糊判断权重矩阵和相对隶属度矩阵的基础上,根据模糊数学综合评判原理,从模糊聚类初选的开拓方案中确定最优开拓方法,通过模糊综合评判确定的最优主、副井开拓方案为竖井+竖井方案.根据矿井提升方式不同,对提出的两种方案进行了技术经济比选,推荐以两矿井集中提升方案为矿井开拓方案.

The selection of mine development plans is a complex process involving multiple factors and indica-tors.In order to reduce the influence of subjective judgment on the selection of mine development plans,taking a uranium mine well as the research object,a fuzzy comprehensive evaluation model was established based on the fuzzy mathematics theory,the fuzzy weights of 10 influencing factors were determined,and the influence degree of the development plan was quantified.Based on the fuzzy judgment weight matrix and the relative membership degree matrix,and in accordance with the principle of fuzzy mathematics comprehensive evaluation,the optimal development method is determined from the initial development schemes of fuzzy clustering.Through fuzzy com-prehensive evaluation,the optimal main and auxiliary shaft development schemes are determined as the vertical shaft and vertical shaft development scheme.According to the different hoisting methods of the mines,a techni-cal and economic comparison was conducted on the two proposed schemes.The comparison results recommend that the centralized hoisting schemes of the two mines be adopted as the mine development schemes.

李从飞

中核内蒙古矿业有限公司,内蒙古呼和浩特 010010

能源科技

铀矿开采模糊综合评判层次分析法(AHP)开拓方案方案优选铀矿井

uranium miningfuzzy comprehensive evaluationanalytic hierarchy process(AHP)de-velopment planscheme optimizationuranium mine well

《铀矿冶》 2026 (2)

61-67,7

10.13426/j.cnki.yky.2025.09.16

评论