以东张水库工程为依托,构建非溢流混凝土重力坝数值模型,系统分析不同工况下坝体孔隙水压力、应力及位移特征.结果表明:随水位升高,孔隙水压力梯度趋于陡峭,校核洪水位下扬压力显著增强;坝体水平应力由底部向顶部递增,竖向应力在高水位下最大值扩展至中部,表明扬压力影响范围扩大;位移方面,水平位移在坝顶达峰值,竖向位移最大值出现在上游坝底 1/3 处,且水位越高,位移越大.

Taking the Dongzhang reservoir project as the research background,a numerical model of a non-overflow concrete gravity dam was established to systematically analyze the pore water pressure,stress distribution,and displacement characteristics of the dam under different operating conditions.The results show that with increasing water level,the pore pressure gradient becomes steeper,and uplift pressure significantly increases under the check flood level.Horizontal stress increases from the base toward the dam crest,while the maximum vertical stress expands toward the middle section at high water levels,indicating a broader influence range of uplift pressure.In terms of deformation,the maximum horizontal displacement occurs at the dam crest,while the maximum vertical displacement appears at approximately one-third of the upstream dam base.Higher water levels correspond to larger displacements.

黄盛润;苏婉婷;蒋起稳;胡俊;徐普

福建省闽江流域中心,福建 福州 350000福建省闽江流域中心,福建 福州 350000福州大学土木工程学院,福建 福州 350108福州大学土木工程学院,福建 福州 350108福州大学土木工程学院,福建 福州 350108

建筑与水利

重力坝扬压力有限元分析应力分布位移分析

Gravity damuplift pressurefinite element analysisstress distributiondisplacement analysis