采用变态整体定床(局部动床)模型实验方法对某引水枢纽除险加固工程各闸水力及冲砂特性进行研究,包括典型流量下各建筑物引水能力、泄流能力、流态、流速分布、冲淤形态等.结果表明:在不同工况闸门调度方案下,均能满足过流要求;在上游闸前右岸增加导流潜水丁坝,能够减少人工弯道进口前泥沙淤积,提高冲砂闸的排沙效率,有效解决闸前淤积问题,可为多泥沙河流枢纽前排砂冲砂布置方案提供依据.

A distorted overall fixed-bed(locally movable-bed)hydraulic model experiment was conducted to investigate the hydraulic and sediment-scouring characteristics of the sluice structures in a water diversion hub reinforcement project.The study examined water diversion capacity,discharge capacity,flow patterns,velocity distribution,and erosion-deposition morphology under typical discharge conditions.The results indicate that all gate operation schemes can meet the required discharge capacity under different operating conditions.By adding a submerged guide spur dike on the right bank upstream of the sluice,sediment deposition at the entrance of the artificial bend was effectively reduced,thereby improving the sediment flushing efficiency of the scouring sluice and mitigating sediment accumulation in front of the gates.The results provide a reference for sediment flushing and layout optimization in diversion hubs located in sediment-laden rivers.

张治浩;董文

新疆兵团勘测设计院集团股份有限公司,新疆 乌鲁木齐 830000新疆兵团勘测设计院集团股份有限公司,新疆 乌鲁木齐 830000

建筑与水利

水工模型泄流方案调度排沙比

Hydraulic modeldischarge schemegate operationsediment flushing ratio

《陕西水利》 2026 (5)

5-8,4