该文针对核电站核岛建设中钢制安全壳容器(CV)筒体模块大型化、薄壁化带来的结构易变形挑战,系统介绍一种吊装运输一体化施工技术.该技术的核心在于通过集成化的工艺设计、专用工装开发及精准的过程控制,将模块的吊装与运输环节作为有机整体进行管理,重点突破巨型筒体结构在吊运全过程中的变形控制难题.所总结的技术要点和实施经验,为后续同类大型薄壁结构模块化工程中吊装运输环节的安全、高效、高质量实施提供重要的技术参考和实践指导.

This paper addresses the challenge of structural deformation inherent in the large-scale and thin-walled characteristics of steel containment vessel(CV)cylindrical modules during nuclear island construction for nuclear power plants.It systematically introduces an integrated hoisting-transportation construction technique.The core of this technique lies in integrating the hoisting and transportation processes into a managed continuum through integrated process design,development of specialized tooling,and precise process control,with a primary focus on overcoming deformation control challenges for the massive cylindrical structure throughout then tire handling operation.The summarized key technical points and implementation experience provide crucial technical references and practical guidance for the safe,efficient,and high-quality execution of hoisting and transportation phases in subsequent large-scale,thin-walled modular projects of a similar nature.

李富军

广东力特工程机械有限公司,广州 510735

信息技术与安全科学

核岛CV筒体吊装运输一体化反应堆模块化

nuclear islandcontainment vessel(CV)integrated hoisting-transportationreactormodularity

《科技创新与应用》 2026 (13)

14-17,4

10.19981/j.CN23-1581/G3.2026.13.004

评论