基于ANP-SD模型的跨海大桥施工阶段造价风险控制与仿真研究OA
Research on Cost Risk Control and Simulation of Construction Stage for Cross-sea Bridges Based on ANP-SD Model
为降低跨海大桥施工阶段的造价风险,本文识别了24个风险指标,并通过网络层次分析法确定权重.基于系统动力学方法(SD),构建了造价风险控制模型,并以HMH跨海大桥为案例验证其有效性.结果表明,项目团队协调、操作能力不匹配、项目进度变更、设计图纸中的错误、漏项,以及施工子项目工艺流程不合理等为主要高风险因素.通过"单一策略控制"和"组合策略控制"进行仿真模拟,结果显示组合策略更有效地降低了风险值.结论表明,高风险指标需优先考虑,并通过减少风险间的交互作用,可以有效降低造价超支的可能性.
In order to reduce the cost overrun risk of cross sea bridge project in the construction stage,this paper discusses the interactive characteristics of cost risk and its control methods.Firstly,the cost risk indicators of 24 construction stages are identified,including project team coordination,mismatching of operation ability,project schedule change risk,design change risk,unreasonable process flow of construction subproject,etc.These indicators may act alone or interactively,resulting in project cost overruns. Then,in order to quantitatively analyze the interaction of these risk factors and their impact on the total cost,a SD model for cost risk assessment of sea crossing bridge construction stage is constructed by using network analytic hierarchy process and system dynamics(SD)method.The network analytic hierarchy process can systematically evaluate the importance of each risk factor and its potential impact on the total cost,and determine the relationship between each factor.The system dynamics method simulates the change and interaction of risk factors in time by constructing a dynamic simulation model. In order to verify the effectiveness of the model,this paper introduces the actual case of HMH sea crossing bridge.Based on this case,an SD model for cost risk assessment of HMH sea crossing bridge in construction phase including control strategy is constructed.The model includes a variety of control strategies,such as reasonable division of bid sections,strict review of on-site visa,strict review of design changes,emphasis on construction bidding,etc.Through simulation,this paper compares the effectiveness of"single strategy control"and"combined strategy control"in reducing cost overrun. The simulation results show that there is a significant interaction between the cost risks in the construction stage,and a single risk control strategy has limited effect in dealing with the complex and changeable risk environment.Single strategy control usually only targets at a specific risk factor,and lacks consideration of other risk factors and their interactions,so it has poor effect in dealing with the comprehensive risks in the complex project environment. In contrast,the use of combination strategy control,that is,the implementation of a variety of risk management measures at the same time,can more effectively reduce the possibility of cost overrun.Through the comprehensive utilization of the advantages of different measures,the combination strategy can reduce the single risk,coordinate and reduce the interaction between various risks,so as to achieve better control effect. The simulation further shows that the combination strategy control can significantly reduce the probability of cost overrun and improve the possibility of successful completion of the project within the budget.This discovery provides a theoretical basis and practical guidance for the cost risk management of large-scale engineering projects such as sea crossing bridges,and helps to improve the project management level and success rate.
袁剑波;曾恬宁;刘顶立;郭平
长沙理工大学 交通运输工程学院,长沙 410114长沙理工大学 交通运输工程学院,长沙 410114长沙理工大学 交通运输工程学院,长沙 410114长沙理工大学 交通运输工程学院,长沙 410114
交通工程
跨海大桥造价风险网络层次分析法系统动力学,组合策略控制
sea crossing bridgecost riskanalytic network processsystem dynamicscombined strategy control
《工程研究——跨学科视野中的工程》 2026 (3)
342-357,16
湖南省交通运输厅科技进步与创新项目(2020039)湖南省研究生科研创新项目(CX20200826)