LJY水库工程埋藏式月牙肋岔管制造安装工艺探讨OA
Discussion on manufacturing and installation technology of buried crescent ribbed bifurcated pipe in LJY Reservoir Project
为满足LJY水库工程城乡供水、灌溉、发电功能,城乡供水洞引水系统根据围岩地质情况共计设置8个月牙肋岔管,文章对供0+159.43地下埋藏式月牙肋岔管的制造、安装工艺控制展开了论述.文章介绍了该埋藏式月牙肋岔管的结构形式及制造安装的主要特点并根据实际情况在制造过程中对月牙肋岔管进行了深化设计,描述了壁厚多级差岔管的施工准备、下料、卷制、焊接、预组装等制造工艺,讨论了洞室内分片岔管运输、拼装、焊接、质量检查等工艺的实施情况.在岔管制造、安装完成后,采用振动时效工艺和水压试验对月牙肋岔管的整体质量进行检测并对实施效果进行探讨.
8 crescent ribbed bifurcated pipes are arranged according to the geological conditions of the surround-ing rock in the urban and rural water supply tunnel diversion system to meet the functions of urban and rural water supply,irrigation,power generation of the LJY Reservoir Project.The paper the manufacturing and in-stallation technology control of the buried crescent rib bifurcated pipe at 0+159.43 m.The paper introduces the structural form and main features of the buried crescent ribbed bifurcated pipe in terms of manufacturing and installation,and further elaborates on the design of the buried crescent ribbed bifurcated pipe according to the actual situation.describes the preparation,cutting,winding,welding,pre-assembly and other manufacturing processes of the crescent ribbed bifurcated pipe and discusses the implementation of transportation,assembly,welding and quality inspection of bifurcated pipe in the chamber.Upon the completion of the bifurcated pipe's manufacturing and installation,vibration aging treatment and hydrostatic pressure testing were employed to assess the overall quality of the crescent-ribbed bifurcated pipe,and the effectiveness of these verification measures is analyzed herein.
何攀;姜鹏
成都市李家岩开发有限公司,四川 成都 610213四川能源发展集团有限责任公司,四川 成都 610213
建筑与水利
埋藏式月牙肋岔管振动时效工艺制造工艺安装工艺
buried crescent ribbed bifurcated pipevibration aging processmanufacturing processinstallation technology
《四川水力发电》 2026 (2)
83-89,7