首页|期刊导航|市政技术|隧道下穿长水机场敏感区域施工技术与稳定性研究

隧道下穿长水机场敏感区域施工技术与稳定性研究OA

Research on Construction Technology and Stability of Tunnel Passing through the Sensitive Area of Changshui Airport

中文摘要英文摘要

为解决隧道下穿机场敏感区域施工中结构安全保障与沉降控制难题,以长水机场隧道下穿工程为研究对象,通过三维有限元模拟与现场监测相结合的方法,探究了施工技术与防护工艺对结构稳定性的影响.研究结果表明:随着隧道的推进,地表沉降量呈"双L"型分布,施工区域影响范围为20.0 m;台阶法施工时垂直于隧道方向的地表沉降曲线呈"V"型,隧道中心线及两侧为防控关键区;三步台阶法+4.0 m间距为优选方案,台阶间距从4.0 m增至8.0 m时,地表沉降增幅达25.86%,三步台阶法对地表沉降控制优于正台阶法,台阶步数影响地表沉降;采用无加固或单一注浆加固、锚杆加固法无法满足沉降要求,而注浆+锚杆综合加固法则可使沉降量降低55.81%,且拱顶沉降效果优于拱底隆起,控制效果排序为综合加固>注浆加固>锚杆加固.该研究成果可为控制隧道下穿机场等敏感区域的沉降与结构安全提供理论依据与工程参考,还可提升施工稳定性.

To address the challenges of structural safety assurance and settlement control during tunnel construction crossing the sensitive airport areas,this study examined the Changshui Airport tunnel project.By integrating 3D fi-nite element simulation with on-site monitoring,the impact of construction techniques and protective measures on stability was investigated.The research findings indicate that the surface settlement exhibits a"double-L"distribu-tion pattern with the tunnel advances,and the construction area affects a range of 20.0 meters;Characteristics of ground settlement perpendicular to the tunnel direction was in a"V"shape by bench method,and the tunnel center-line and both flanks were critical control zones;The three-step bench method with a 4.0 m spacing emerged as the optimal solution.When bench spacing increased from 4.0 m to 8.0 m,the surface settlement increased by 25.86%.The three-step bench method was superior to the conventional bench method in controlling surface subsidence and the number of bench steps influenced settlement.Unreinforced or single grouting/bolting reinforcement failed to meet settlement requirements.The combined grouting+bolting reinforcement reduced settlement by 55.81%.The effect of arch crown settlement was better than that of arch bottom heave.The control effectiveness ranking is:combined reinforcement>grouting reinforcement>bolting reinforcement.This research provides theoretical foundations and engineering references for controlling settlement and structural safety in sensitive areas such as tunnels crossing air-ports,and enhancing construction stability as well.

尹兴勇

天津中铁工程检测有限责任公司,天津 300000

交通工程

隧道施工现场监测稳定性台阶法台阶间距综合加固

tunnel constructionon-site monitoringstabilitybench methodstep spacingcomprehensive reinforcement

《市政技术》 2026 (3)

201-209,9

10.19922/j.1009-7767.2026.03.201

评论