叶巴滩水电站大坝深卸荷置换洞施工环境地形复杂,该工程主要为开挖四类松弛卸荷岩体,围岩岩体较差,施工中存在氡子体放射性有害气体及岩爆可能,需加强散烟通风和防护.施工时采取洞室爆破并进行通风散烟,具体流程为:先测量并钻孔,再装填炸药进行联网起爆,然后通风散烟、排险支护,最后出渣清底进行下一循环的施工.通过严格控制爆破参数及施工质量,如残孔率及质点振速等指标,保证深卸荷置换洞爆破开挖取得良好的整体效果,满足设计要求.
The construction environment and topography of the deep unloading and replacement tunnel of the Yebatan Hydropower Project Dam are complex.This project mainly involves excavating four types of loose unloading rock masses,with relatively poor surrounding rock quality.During construction,there is a possibility of radioactive harmful gas from radon and rock bursts,requiring enhanced smoke ventilation and protection.During construction,blasting is carried out in the tunnel chamber followed by ventilation and smoke exhaust.The specific process is:first measure and drill holes,then charge explosives for networked detonation,followed by ventilation and smoke exhaust,risk removal support,and finally mucking and bottom cleaning for the next excavation cycle.By strictly controlling blasting parameters and construction quality,such as residual hole rate and particle vibration velocity,the blasting excavation of the deep unloading and replacement tunnel ensures a good overall effect and meets the design requirements.
丁品良;李高慧;王杰
中国水利水电第七工程局有限公司,四川 成都 610213中国水利水电第七工程局有限公司,四川 成都 610213中国水利水电第七工程局有限公司,四川 成都 610213
天文与地球科学
叶巴滩水电站置换洞开挖质量控制爆破参数
Yebatan Hydropower Projectreplacement tunnelexcavation quality controlblasting parameters