苏州港太仓四期自动化集装箱码头堆场布置技术研究OA
Research on Layout Technologies for Phase IV Automated Container Terminal Yard at Taicang Harbor of Suzhou Port
针对引桥式集装箱码头水平运输路径长的运行特点,依托苏州港太仓港区四期工程(长江流域首个且最大规模自动化港区),研究自动化堆场布置关键技术.堆场采用平行码头前沿线布置模式,通过优化水平运输路径实现交通组织效率提升;国内首次大规模应用40 m大轨距双悬臂自动化轨道吊,构建内外集卡物理隔离作业体系,结合仿真模拟确定设备最优参数,在保障作业效率的前提下,实现堆场容量与利用率的最大化,为长江流域引桥式码头自动化升级提供技术范式.
In view of long distance of horizontal transport at the bridge-approach container terminals,key technologies for the layout of automated yards were studied on the basis of phase IV project at Taicang Harbor of Suzhou Port,which was the first and largest automated terminal in the Yangtze River basin.Subject to an pattern being parallel to the quay line,the traffic organization efficiency was enhanced through the optimization of horizontal transport routes in the yard.As a pioneer who firstly adopted 40 m gauge double-cantilever automated rail-mounted cranes in large quantities in China,the port authority built an operation system that physically separated the trucks in the port from that out of the port.In addition,the simulation modeling was employed to determine the optimal equipment parameters.The yard capacity and utilization ratio were maximized subject to the efficiency being guaranteed.This research may serve as a technical reference for the automated upgrading of the bridge-approach terminals in the Yangtze River basin.
施晓迪;沈燕娣;何继红;兰加智
中交第三航务工程勘察设计院有限公司,上海 200032中交第三航务工程勘察设计院有限公司,上海 200032中交第三航务工程勘察设计院有限公司,上海 200032中交第三航务工程勘察设计院有限公司,上海 200032
交通工程
自动化集装箱堆场引桥式码头平面布局自动化轨道吊大轨距双悬臂仿真模拟
automated container yardbridge-approach terminalplan layoutautomated rail-mounted cranewide-gauge double-cantileversimulation modeling