新建100MW机组给水调节阀堵塞原因及解决措施OA
Causes and Solutions for Blockage of Feedwater Control Valves in Newly Built 100 MW Units
针对新建100 MW机组给水调节阀的堵塞问题,分析了堵塞的成因,主要包括施工残留物、管道锈蚀、氧化膜脱落、调节阀结构设计及运行方式等因素,提出了相应的解决办法,包括严格控制给水pH、调整运行压力、定期清理设备以及改进调节阀结构等.
Addressing the blockage issue of feedwater control valves in newly built 100 MW units,the causes of blockage were analyzed,mainly including construction residue,pipeline corro-sion,oxide film shedding,control valve structural design,and operation mode.Corresponding solu-tions were proposed,including strictly controlling feedwater pH,adjusting operating pressure,regu-lar equipment cleaning,and improving the control valve structure.
汪明宇;张小磊;孙玮;宋斌斌;李辉;庞振振
首钢京唐钢铁联合有限责任公司,河北 唐山 063200首钢京唐钢铁联合有限责任公司,河北 唐山 063200首钢京唐钢铁联合有限责任公司,河北 唐山 063200首钢京唐钢铁联合有限责任公司,河北 唐山 063200首钢京唐钢铁联合有限责任公司,河北 唐山 063200首钢京唐钢铁联合有限责任公司,河北 唐山 063200
信息技术与安全科学
100MW机组给水调节阀堵塞原因
100 MW unitfeedwater control valvecauses of blockage
《冶金动力》 2026 (1)
57-59,3