基于CTCS-3/CTCS-2临时级间转换点设置方案研究及实践OA
Research and Practice on Setting Scheme of Temporary Transition Points Based on CTCS-3 and CTCS-2
新建高铁接入既有枢纽时信号系统改造面临严峻挑战,其核心矛盾在于新建高铁联调联试与既有线列车安全运营的时空冲突协调难度极大,现有研究对此缺乏系统性解决方案.以渝昆高铁接入宜宾(泸州)枢纽工程为例,深入剖析工程难点,创新性提出新建高铁与既有线间设置CTCS-3/CTCS-2动态降级过渡机制关键技术研究.该技术方案经实践验证:设置CTCS-3/CTCS-2临时级间转换点成功地解决了新建渝昆调度台同步管理联调联试与运营冲突的技术难题,符合列车控制系统等规范标准要求,满足项目建设进度、运营行车需求,联调联试进度提升71.4%,既有线信号系统故障率控制在0.2次/万列公里以内.研究成果可为类似铁路工程提供借鉴.
The connection of newly-constructed high-speed railways to the signaling systems of existing railway hubs involves severe challenges.The core conflict lies in the extreme difficulty of coordinating space and time conflicts between the integrated testing and commissioning of newly-built railways and the safe train operation on existing lines.In the existing research,there is a lack of systematic solutions to this issue.Taking the project of connecting the Chongqing-Kunming High-Speed Railway to the Yibin(Luzhou)Hub as an example,this paper conducts an in-depth analysis of engineering challenges and proposes key technologies for establishing a transition mechanism for dynamic downgrade between CTCS-3 and CTCS-2 at the interface between newly-built and existing lines as an innovative solution.The proposed solution has been service-proven,demonstrating that setting CTCS-3/CTCS-2 temporary transition points successfully resolves the technical difficulty of managing conflicts between integrated testing and commissioning and operational services under the newly-established Chongqing-Kunming dispatching console.This new solution complies with train control system specifications and standards,meets project timelines and operational requirements,accelerates the progress of integrated testing and commissioning by 71.4%,and restricts the failure rate of signaling systems for existing lines to ≤ 0.2 incidents per 10,000 train-kilometers.The research findings provide valuable insights for similar railway projects.
杨朝华
京昆高速铁路西昆有限公司,重庆 400023
交通工程
CTCS-3CTCS-2等级转换联调联试动态降级临时转换点
CTCS-3CTCS-2level transitionintegrated testing and commissioningdynamic downgradetemporary transition point
《铁路通信信号工程技术》 2026 (2)
36-41,75,7
中国国家铁路集团有限公司科技研究开发计划项目(N2024G050)
评论