首页|期刊导航|陕西水利|龙羊峡一期抽水蓄能电站进/出水口三维有限元分析

龙羊峡一期抽水蓄能电站进/出水口三维有限元分析OA

Three-Dimensional Finite Element Analysis of the Intake/Outlet of the First Stage Longyangxia Pumped Storage Power Station

中文摘要英文摘要

应用ANSYS软件对龙羊峡一期抽水蓄能电站的下库进/出水口进行全面的静力与动力结构分析,旨在探究在完建期与运行期阶段,进/出水口的自振频率特性,并通过反应谱法对进/出水口的应力水平与稳定性进行深入研究.结果表明,在地震作用下,进/出水口顶部及拦污栅墩等特定区域的最大拉应力显著超过了该区域混凝土的理论抗拉强度极限.因此,为有效预防混凝土结构的开裂现象,在这些关键部位配置一定的钢筋,以增强结构的抗拉性能和整体稳定性.对进/出水口进行抗滑、抗浮及抗倾覆稳定性分析,结果显示塔身的稳定性良好,完全符合相关规范的要求.

A comprehensive static and dynamic structural analysis of the lower reservoir intake/outlet of the first stage Longyangxia pumped storage power station was conducted using the ANSYS software.The study aimed to investigate the natural frequency characteristics of the intake/outlet during both the completion and operational phases.Furthermore,a deep analysis of the stress levels and stability of the intake/outlet was performed using the response spectrum method.The results indicate that under seismic action,the maximum tensile stress in specific areas,such as the top of the intake/outlet and the trash rack piers,significantly exceeds the theoretical tensile strength limit of the concrete in these zones.Therefore,to effectively prevent cracking of the concrete structure,a certain amount of reinforcement is required in these critical areas to enhance the tensile performance and overall stability of the structure.Stability analyses against sliding,flotation,and overturning were also carried out for the intake/outlet.The results demonstrate that the stability of the tower structure is excellent and fully complies with the requirements of the relevant codes and standards.

He Lei

PowerChina Northwest Engineering Corporation Limited,Xi'an 710000,Shaanxi

建筑与水利

抽水蓄能进/出水口静力分析动力分析拉应力稳定性

Pumped storageintake/outletstatic analysisdynamic analysistensile stressstability

《陕西水利》 2026 (1)

1-3,8,4